Previous works

Selected projects completed with leading owners, contractors, and consultants.

  • Mivida Parcel 21

    Type
    Residential
    Owner
    Emaar Misr
    Main contractor
    CRC Dorra
    Consultant
    AMG - Al Amar Consulting Group
    Completion
    Dec 2016 · Feb 2017
    Scope of work
    Full Concrete Structure Works - 18 Villas Plastering Works - 10 Villas
  • Mivida Parcel 17

    Type
    Residential
    Owner
    Emaar Misr
    Main contractor
    A.C.C | Arabian Construction Company
    Consultant
    EHAF - Consulting Engineers
    Completion
    Mar 2017
    Scope of work
    Finishing (Interior & Exterior plastering, Interior & Exterior painting, Supply & Apply gypsum Board, Full electrical Works, tiles Installing) - 45 Villas
  • Mivida Parcel 8

    Type
    Residential
    Owner
    Emaar Misr
    Main contractor
    A.C.C | Arabian Construction Company
    Consultant
    EHAF - Consulting Engineers
    Completion
    Sep 2017
    Scope of work
    Finishing (Interior & Exterior plastering, Interior & Exterior painting, Supply & Apply gypsum Board, Full electrical Works, tiles Installing) - 21 Villas
  • Mivida Parcel 1A

    Type
    Residential
    Owner
    Emaar Misr
    Main contractor
    CRC Dorra
    Consultant
    Turner Construction International
    Completion
    Dec 2018
    Scope of work
    Full Concrete Structure Works, Exterior Plastering, Exterior Painting Works - 15 Villas
  • Al Maqsad N.A.C - R3 (D4, D5)

    Type
    Residential
    Owner
    New Urban Communities Authority & City Edge Development
    Main contractor
    CRC Dorra
    Consultant
    5+ UDC Consulting - Urban Development Consortium
    Completion
    Apr 2018
    Scope of work
    Concrete Structure Works - 73 Villas
  • D1 & D2 Buildings - CFC Podium Zone

    Type
    Administrative
    Owner
    Al Futtaim Misr for Development and Investment
    Main contractor
    A.C.C | Arabian Construction Company
    Consultant
    RMC - Raafat Miller Consulting
    Completion
    Oct 2019
    Scope of work
    Masonry Works, Interior & Exterior Plastering Works - 2 Buildings (7 Floors Each)
  • Capital East Residence "1"

    Type
    Residential
    Owner
    Tabarak Developments
    Main contractor
    Tabarak Developments
    Consultant
    Tabarak Developments
    Completion
    Oct 2022
    Scope of work
    Concrete Structure Works, Electrical Works, Plumbing Works - 3 Buildings (10 Floors Each)
  • Rawdet Elobour - East Belbeis Road

    Type
    Residential, Commercial
    Owner
    New Urban Communities Authority
    Main contractor
    Harby Nazeer Construction
    Consultant
    Faculty of Engineering - Ain Shams University
    Completion
    Oct 2023
    Scope of work
    Full Electrical Works, Full Plumbing Works - 11 Buildings (396 Residential Units, 44 Commercial Units)
  • Sakan Ahl Misr "Ahalina 6" - Sinoma

    Type
    Residential, Commercial
    Owner
    Urban Development Fund & Engineering Authority of Armed Forces
    Main contractor
    Sinoma CDI
    Consultant
    Vision Consultant
    Completion
    Apr 2026
    Scope of work
    Concrete Structure Works - 2 Buildings (11 Floors Each)
  • Sakan Ahl Misr "Ahalina 6" - Al Salheiia

    In progress
    Type
    Residential, Commercial
    Owner
    Urban Development Fund & Engineering Authority of Armed Forces
    Main contractor
    Al Salheiia
    Consultant
    HDEC Engineering Consulting
    Scope of work
    Concrete Structure Works, Interior Plastering - 3 Buildings (232 Residential Units, 24 Commercial Units) Electrical Works, Plumbing Works, Exterior Plastering - 4 Buildings (320 Residential Units, 24 Commercial Units)